HEAVY RAINS DELAY THE RECONNECTION OF THE GREAT EAST ROAD.

 

Heavy rains have delayed the reconnection of the Great East Road at Kankhumba stream in Rufunsa district where culverts were washed away on Thursday afternoon.

In a joint statement issued by Lusaka Provincial Administration Principal Public Relations Officer Logic Lukwanda and Ministry of Defence Principal Public Relations Officer  Paul Shalala, initially, traffic was expected to begin flowing through a detour being put by the Road Development Agency and Zambia National Service.

Works commenced yesterday and engineers continued working throughout the night to ensure restoration of traffic.

The placing of culverts on the detour that is crossing the same stream is underway as works have reached 60 percent before the diversion is ready for traffic.

Engineers on the ground have projected that traffic will be restored late afternoon today as speed in works has been prioritized.

The current situation is that there is traffic build up both east and west bound leaving motorists who are going both ends stranded except for busses who exchanging passengers and good and making U-turns.

ZNS yesterday delivered Acrow bridge panels ahead of their installation for a temporal bridge to be erected, whose works are expected to be complete in 72 hours.

ZNS Commander Lt Gen Eng.Maliti Solochi and Lusaka Province Minister Sheal Mulyata Visited the site to appreciate the magnitude of the problem.

 

By Evans Sinjela